June's record-setting rain pushed Lexington's stormwater system past its limits. Now comes the analysis

Josh James
/
WUKY

Heavy storms in June presented a test for Lexington's stormwater system and in some areas it failed. This week, the city council hear analysis of what happened and what fixes the city has planned.

According to the Lexington Herald-Leader, June 2026 was the fourth rainiest June on record, topping 10.5 inches of rain. The outcome: Dozens of flooded structures, 86 washed-out streets, and a number of evacuations.

"The worst damage happened June 22. A downtown rain gauge recorded 2.85 inches of rain over 8.5 hours," CivicLex's Aaron Mudd says. "The presentation says the rain overwhelmed older infrastructure that was built before the stormwater manual guidelines in 2001."

Some of the hardest-hit areas included Ashland and locations between Harrodsburg Road and Nicholasville Road. The council will hear about updates to the city's stormwater priority list, which includes about 30 capital projects.

"Projects in Joyland and on Cooper Drive have been completed. Work is underway at Mentelle Park, and future advancements will take place in Idle Hour, Gainesway, Lane Allen/Darien, Hume Road, South Elkhorn, and Southland Drive," Mudd says.

Planners also want to update the city's 3-1-1 reporting system for stormwater, track incoming NOAA weather data, and make changes to Lexington's stormwater severity scoring system.